Laboratory & Office Design & Fit Out, Oxfordshire

By Glenside, Reading.

Oxfordshire

21 weeks

4,900 sq ft

Specialist Product Manufacturer

Laboratory regeneration.

Having worked with us on previous laboratory and other projects over some years, our client selected Glenside to provide a turnkey project to develop an old laboratory and office space into a modern laboratory suite. From initial concepts, through detailed design and then to complete fulfilment of the project, we worked in close collaboration with the client stakeholders to provide an impressive space in a compact timescale.

Laboratory regeneration.

Having worked with us on previous laboratory and other projects over some years, our client selected Glenside to provide a turnkey project to develop an old laboratory and office space into a modern laboratory suite. From initial concepts, through detailed design and then to complete fulfilment of the project, we worked in close collaboration with the client stakeholders to provide an impressive space in a compact timescale.

Laboratory regeneration.

Having worked with us on previous laboratory and other projects over some years, our client selected Glenside to provide a turnkey project to develop an old laboratory and office space into a modern laboratory suite. From initial concepts, through detailed design and then to complete fulfilment of the project, we worked in close collaboration with the client stakeholders to provide an impressive space in a compact timescale.

A complete visual transformation.

The existing facilities were generally of 1980s construction, and comprised old concrete ceilings, presence of asbestos, and dilapidated furniture and finishes.   


The space is now barely recognisable, with metal suspended ceilings, new glazed and solid partitioning and doors, new safety flooring and full decoration in cleanable finishes. We also provided a complete new installation of resilient lab benching, storage, racking and seating.

A complete visual transformation.

The existing facilities were generally of 1980s construction, and comprised old concrete ceilings, presence of asbestos, and dilapidated furniture and finishes.   

The space is now barely recognisable, with metal suspended ceilings, new glazed and solid partitioning and doors, new safety flooring and full decoration in cleanable finishes. We also provided a complete new installation of resilient lab benching, storage, racking and seating.

A complete visual transformation.

The existing facilities were generally of 1980s construction, and comprised old concrete ceilings, presence of asbestos, and dilapidated furniture and finishes.   



The space is now barely recognisable, with metal suspended ceilings, new glazed and solid partitioning and doors, new safety flooring and full decoration in cleanable finishes. We also provided a complete new installation of resilient lab benching, storage, racking and seating.

A complete technical transformation.

Similarly, the existing technical infrastructure was dated and inadequate. Our project included complete new ventilation and temperature control systems, replacement electrical, data, lighting, nitrogen, compressed air, water, sprinkler and fire detection systems. The project also included the supply and installation of new fume cupboards and local extract ventilation.

A complete technical transformation.

Similarly, the existing technical infrastructure was dated and inadequate.



Our project included complete new ventilation and temperature control systems, replacement electrical, data, lighting, nitrogen, compressed air, water, sprinkler and fire detection systems.


The project also included the supply and installation of new fume cupboards and local extract ventilation.

A complete technical transformation.

Similarly, the existing technical infrastructure was dated and inadequate. Our project included complete new ventilation and temperature control systems, replacement electrical, data, lighting, nitrogen, compressed air, water, sprinkler and fire detection systems.


The project also included the supply and installation of new fume cupboards and local extract ventilation.

A turnkey process.

Glenside’s package included concept and detailed design, building control assistance, asbestos removal, full project delivery and final O&M/certification.  The project was completed within an operational building in line with the agreed project programme.


The space is now operational, and we are preparing for the development of a further laboratory space on the same site.

A turnkey process

Glenside’s package included concept and detailed design, building control assistance, asbestos removal, full project delivery and final O&M/certification.  The project was completed within an operational building in line with the agreed project programme. The space is now operational, and we are preparing for the development of a further laboratory space on the same site.

A turnkey process.

Glenside’s package included concept and detailed design, building control assistance, asbestos removal, full project delivery and final O&M/certification.


The project was completed within an operational building in line with the agreed project programme. The space is now operational, and we are preparing for the development of a further laboratory space on the same site.

Before & After.

A room with a lot of windows and a machine on a table
A woman in a lab coat is walking down a hallway in a laboratory.

A vibrant new laboratory.

More of our projects:

Marketing Agency in Buckinghamshire

Global Pharmaceutical Company in Oxfordshire

Food Supplier in Berkshire

Get in touch.

A woman is walking through a lobby with a welcome sign on the wall.

For more details on how we can help or to book a consultation at our showroom, please call us on 0118 214 7890 or fill out the form and we will get back to you soon.

Contact Us

Share by: